The major renovation of the overpass on Polyarna Street in Kyiv's Obolon district is in progress. The completion of the main construction works is scheduled for the end of the year. According to Kyivavtodor, the current efforts are focused on the section of the overpass heading towards Heroes of Dnipro Street.
As of October 23, the last 32 beams of the span structure have been installed, with a total of 64 beams in the construction. New supports and girders have also been set up.
“We are entering the next phase: reinforcing the spans, installing the monolithic slab for the roadway and sidewalk, and mounting the cornice blocks and barriers,” reported the Kyivavtodor.
To maintain traffic flow for vehicles and pedestrians, all work is being carried out with partial phased restrictions.
The primary construction works, with the complete restoration of traffic, are expected to finish by the end of the year.
Simultaneously, work is ongoing to set up bike and pedestrian paths, enhance the underground pedestrian crossing, and improve the surrounding area.